In 2013, Rettler Corporation worked with the Nicolet Union School District to develop a master plan for the high school athletic facilities including a new multi-use synthetic turf stadium with an expanded track and updated field events, a 14 court tennis complex, and an additional synthetic turf soccer stadium. This project also included a digital video board and LED athletic field lighting for all courts and fields. Construction began in the fall of 2022 beginning with the 3 tier tennis complex, built into the grade using big block modular retaining walls. The remainder of the project was constructed spring and summer of 2023 and opened to accommodate all fall sports.
Scope of Services: Master Planning, Design, Engineering, Permitting, Bidding, Construction Management
Budget: $10,750,000
Completion: August 2023