top of page

Nicolet Union High School

Glendale, WI
In 2013, Rettler Corporation worked with the Nicolet Union School District to develop a master plan for the high school athletic facilities including a new multi-use synthetic turf stadium with an expanded track and updated field events, a 14 court tennis complex, and an additional synthetic turf soccer stadium. This project also included a digital video board and LED athletic field lighting for all courts and fields. Construction began in the fall of 2022 beginning with the 3 tier tennis complex, built into the grade using big block modular retaining walls. The remainder of the project was constructed spring and summer of 2023 and opened to accommodate all fall sports.

Scope of Services: Master Planning, Design, Engineering, Permitting, Bidding, Construction Management

Budget: $10,750,000

Completion: August 2023
DJI_20240603141350_0870_D.jpg
bottom of page